Which sequence best describes risk management steps per ISO 14971?

Prepare for the CMMA CAMESE Exam with comprehensive study materials. Use flashcards and multiple-choice questions with hints and detailed explanations. Maximize your success and ace your test!

Multiple Choice

Which sequence best describes risk management steps per ISO 14971?

Explanation:
ISO 14971 risk management follows a lifecycle: identify potential hazards, assess the associated risk by estimating and evaluating it, implement appropriate risk controls to reduce that risk, and then monitor and verify the effectiveness of those controls while keeping thorough documentation in a risk management file. The option that aligns with this sequence starts with identifying hazards, then estimating and evaluating risks, then implementing risk controls, and finally monitoring/verifying effectiveness with a documented risk management file. This mirrors the standard’s structure: risk analysis (hazard identification, risk estimation, risk evaluation), risk control (selection and implementation of controls with residual risk assessment), and ongoing verification and documentation. The other options either skip the evaluation step, reverse the order by implementing controls before estimating risks, or describe actions (like discontinuing development) that aren’t how ISO 14971 guides risk management.

ISO 14971 risk management follows a lifecycle: identify potential hazards, assess the associated risk by estimating and evaluating it, implement appropriate risk controls to reduce that risk, and then monitor and verify the effectiveness of those controls while keeping thorough documentation in a risk management file. The option that aligns with this sequence starts with identifying hazards, then estimating and evaluating risks, then implementing risk controls, and finally monitoring/verifying effectiveness with a documented risk management file. This mirrors the standard’s structure: risk analysis (hazard identification, risk estimation, risk evaluation), risk control (selection and implementation of controls with residual risk assessment), and ongoing verification and documentation. The other options either skip the evaluation step, reverse the order by implementing controls before estimating risks, or describe actions (like discontinuing development) that aren’t how ISO 14971 guides risk management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy